Cernavodă: The Cernavodă refurbishment gained its first big slice of European money on 16 November 2026, when Romanian nuclear operator Nuclearelectrica and the European Investment Bank signed a €400 million financing agreement for Unit 1 of the plant on the Danube.
The loan forms the first half of an €800 million package that the EIB board approved in July 2026. Nuclearelectrica expects to sign a second €400 million agreement in 2027, so the full EIB envelope should be in place well before the reactor goes offline for its main works.
The Cernavodă refurbishment carries a total price tag of about €3.1 billion. Its purpose is to extend the operating life of Unit 1 by a further 30 years, keeping a reactor that entered commercial service in 1996 on the grid until around 2060. The EIB money covers roughly a quarter of the cost, excluding financing expenses.
Nuclearelectrica plans to fund the remainder from its own cash flow and from loans by commercial banks, export credit agencies and other international lenders. Chief financial officer Daniel Adam described the deal as the largest EIB financing ever granted to a company in Romania and said it confirmed lenders’ confidence in the project and in the long-term value of nuclear power.
The Cernavodă refurbishment now sits in its second phase, which covers preparatory works, procurement of major equipment, site infrastructure and the financing structure. The decisive third phase runs from 2027 to 2030. During that window the operator will shut Unit 1 down and replace key reactor components, including the fuel channels that wear out over decades of operation.
The stakes for Romania’s power system are high. Unit 1 produces about 5 million megawatt hours a year, and the two existing Cernavodă reactors together supply around 20% of the country’s electricity. A long outage without a credible return date would force Bucharest to buy more power on regional markets at a time of tight winter supply.
For the EU, the signature shows the bank backing nuclear life extension at a scale it rarely reaches. Several member states have pressed the EIB to treat low-carbon baseload power as part of the Union’s climate and security goals. Romania’s national energy and climate plan counts on nuclear output to meet its 2030 emissions targets.
The Cernavodă refurbishment also fits a wider pattern across central and eastern Europe. Governments there want to lengthen the life of existing reactors while new units remain years away. Life extension costs less per megawatt hour than new build and keeps skilled staff and supply chains in place.
The next milestones are the second EIB tranche in 2027 and the start of the reactor shutdown. If Nuclearelectrica keeps to its schedule, the Cernavodă refurbishment will return Unit 1 to the grid by 2030 and secure a fifth of Romania’s power for another three decades.